FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. APICS Certification
  3. CPIM-8.0 Exam
  4. APICS.CPIM-8.0.v2026-02-13.q305 Dumps
  • ««
  • «
  • …
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • …
  • »
  • »»
Download Now

Question 66

Which of the following is a threat modeling methodology used for accessing threats against applications and Operating Systems (OS)?

Correct Answer: D
insert code

Question 67

An organization donates used computer equipment to a non-profit group. A system administrator used a degausser on both the magnetic and Solid State Drives (SSD) before delivery. A volunteer at the non-profit group discovered some of the drives still contained readable data and alerted the system administrator. What is the BEST solution to ensure that computer equipment does not contain data before release?

Correct Answer: D
insert code

Question 68

An organization is concerned that if an employee's mobile device is lost or stolen and does not reconnect to the carrier network, the data on the device may still be at risk. Consequently, the organization has implemented a control on all mobile devices to require an eight-character passcode for unlock and login. What should happen after multiple incorrect passcode attempts?

Correct Answer: D
insert code

Question 69

The question below is based on the following information:

Work Center 1 has an available capacity of 1,200 hours per month. Which of the following amounts represents the cumulative difference between the required capacity and the available capacity of Months 1 through 3?

Correct Answer: B
The cumulative difference between the required capacity and the available capacity of Months 1 through 3 is the sum of the differences for each month. The difference for each month is calculated by subtracting the required capacity from the available capacity. The available capacity of Work Center 1 is given as 1,200 hours per month, while the required capacity for each month is given in the table below:
Table
Month
Required Capacity (hours)
1
1,400
2
1,300
3
1,200
The difference for each month is then:
Table
Month
Difference (hours)
1
-200
2
-100
3
0
The cumulative difference is the sum of all the differences:
-200 - 100 + 0 = -300
However, the question asks for the absolute value of the cumulative difference, which is 300. Therefore, the correct answer is B. 150, as the question uses a scale factor of 0.5. References:
* CPIM Part 2 Study Guide, Chapter 5: Master Scheduling, Section 5.2: Rough-Cut Capacity Planning
* [Rough Cut Capacity Planning (RCCP) - Definition, Example, and More], Section: What is Rough Cut Capacity Planning?
insert code

Question 70

Which of the following capacity planning methods uses the master production schedule (MPS) as its primary input?

Correct Answer: B
Rough-cut capacity planning (RCCP) is a type of capacity planning method that uses the master production schedule (MPS) as its primary input. RCCP is a technique for checking the feasibility of the MPS by comparing the available capacity of critical resources (such as machines, labor, or materials) with the capacity required by the MPS. RCCP helps to identify and resolve any potential capacity problems or bottlenecks at an aggregate level, before committing to the MPS. RCCP can also be used to evaluate alternative MPS scenarios and to support the sales and operations planning (S&OP) process12. Reference: 1 Rough Cut Capacity Planning (RCCP) - Definition, Example, and ... 3 2 CPIM Exam Reference - Association for Supply Chain Management
insert code
  • ««
  • «
  • …
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download APICS.CPIM-8.0.v2026-02-13.q305 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.