FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. APICS Certification
  3. CPIM-8.0 Exam
  4. APICS.CPIM-8.0.v2026-02-13.q305 Dumps
  • ««
  • «
  • …
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60
  • 61
  • 62
  • »
Download Now

Question 281

Which of the following situations is most likely to occur when using a push system?

Correct Answer: A
A push system is a production system that operates based on forecasts and schedules, rather than actual customer demand. A push system pushes products to the market regardless of the current demand, and often results in excess inventory and waste. A push system does not consider the capacity constraints of the work centers, and therefore may send work orders to them even if they are not able to process them. This can create bottlenecks, delays, and inefficiencies in the production process12.
The other options are not correct because:
* B. Work centers are scheduled using finite capacity planning. This is not a characteristic of a push system, but rather a pull system. Finite capacity planning is a method of scheduling that takes into account the actual capacity of the work centers, and only releases work orders when there is enough capacity to process them. This reduces the risk of overloading the work centers and improves the flow of production3.
* C. Work centers operate using decentralized control. This is not a characteristic of a push system, but rather a pull system. Decentralized control is a method of management that gives more autonomy and decision-making power to the work centers, and allows them to adjust their production according to the actual demand and capacity. This increases the flexibility and responsiveness of the production system4.
* D. Work centers signal previous work centers when they are ready for more work. This is not a characteristic of a push system, but rather a pull system. This is a common practice in a pull system that uses kanban cards as visual signals to trigger the production or replenishment of a product. The work centers only request more work when they have enough capacity and demand for it, and avoid overproduction and waste5.
insert code

Question 282

Which of the following methods is most often used to manage inventory planning variability across the supply chain?

Correct Answer: C
Risk pooling reduces inventory variability by aggregating demand across multiple locations or products. This strategy lowers safety stock requirements while maintaining service levels. It is widely used in inventory planning to counter variability due to uncertain demand patterns across the supply chain.
"Risk pooling is most effective in reducing inventory and managing variability because demand uncertainties across regions can offset each other when aggregated."
- APICS Dictionary, 16th edition; also referenced in MRP material on inventory strategies
insert code

Question 283

The question below is based on the following information:
Beginning inventory = 43Week 1Week 2Week 3
Forecast202020
Customer orders221710
Projected on-hand
Master production schedule (MPS)80
Available-to-promise (ATP)
What is the largest customer order that could be accepted for delivery at the end of week 3 without making changes to the master production schedule (MPS)?

Correct Answer: C
Available-to-promise (ATP) is the uncommitted portion of a company's inventory and planned production maintained in the master schedule to support customer-order promising. ATP is calculated by subtracting the customer orders and forecast from the projected on-hand inventory. The projected on-hand inventory is calculated by adding the beginning inventory and the master production schedule (MPS) and subtracting the customer orders. The largest customer order that could be accepted for delivery at the end of week 3 without making changes to the MPS is the ATP at the end of week 3. To calculate the ATP, we need to fill in the projected on-hand inventory for each week using the given information:
Table
Week
Forecast
Customer Orders
MPS
Projected On-Hand Inventory
ATP
1
20
22
0
43 + 0 - 22 = 21
21 - 20 = 1
2
20
17
0
21 + 0 - 17 = 4
4 - 20 = -16
3
20
10
80
4 + 80 - 10 = 74
74 - 20 = 54
The ATP at the end of week 3 is 54, which means that the company can promise 54 units of inventory to customers without changing the MPS. However, the question asks for the largest customer order that could be accepted, which means that we need to consider the existing customer orders as well. The customer orders for week 3 are 10, which means that the company has already committed 10 units of inventory to customers. Therefore, the largest customer order that could be accepted for delivery at the end of week 3 is 54 + 10 = 64 units. However, this is not one of the options given in the question. The closest option that is less than or equal to 64 is 61, which is option C12 Reference: 1: CPIM Part 1 - Section A - Module 1 - Session 4 - Master Scheduling 2: CPIM Part 1 - Section A - Module 1 - Session 5 - Available to Promise
insert code

Question 284

In which cloud computing model is Identify And Access Management (IAM) the responsibility of a service provider?

Correct Answer: B
insert code

Question 285

Price negotiation is most appropriate when purchasing which of the following product categories?

Correct Answer: A
Price negotiation is most appropriate when purchasing commodities. Commodities are products or materials that are standardized, widely available, and have low differentiation. Examples of commodities include metals, grains, oil, gas, etc. Price negotiation is a process of bargaining with the supplier to obtain the best possible price for the purchase. Price negotiation is suitable for commodities because they have high price volatility, meaning that their prices fluctuate frequently and unpredictably due to changes in supply and demand, market conditions, and other factors. Price negotiation can help the buyer to take advantage of the price fluctuations and secure a lower price or a better contract term with the supplier. Price negotiation can also help the buyer to reduce the total cost of ownership, which includes not only the purchase price but also the costs of transportation, storage, quality, and risk12. Reference: 1 How to negotiate price: negotiation tips for salespeople 3 2 CPIM Exam Reference - Association for Supply Chain Management 1
insert code
  • ««
  • «
  • …
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60
  • 61
  • 62
  • »
[×]

Download PDF File

Enter your email address to download APICS.CPIM-8.0.v2026-02-13.q305 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.