When the last operation is on the routing is scheduled first and is scheduled for complete at the due date, this is called:
The Economic-order quantity will increase as the annual demand and the cost of ordering decrease, and it will decrease as the cost of carrying inventory and the unit cost increase.
Checking is a two step process. First the order must be scheduled to see when the capacity is needed, and second, the load on work centers must be checked in that period.