| Exam Code/Number: | RE18Join the discussion |
| Exam Name: | BCS Practitioner Certificate in Requirements Engineering 2018 |
| Certification: | BCS |
| Question Number: | 80 |
| Publish Date: | Jul 17, 2026 |
|
Rating
100%
|
|
Life Extenders is a not-for-profit organization, which renovates donated furniture to sell in its high street shop; any profit it makes is given to local charities. The operations director is planning a small project to implement a website to support the organization.
The business analyst assigned to work on this project is in the process of identifying stakeholder roles.
The following have been suggested:
(A) Members of the public could be customers of Life Extenders.
(B) Members of the public could be suppliers of Life Extenders.
(C) Life Extenders is a partner of other local charities.
(D) Life Extenders is a regulator as it is a not-for-profit
organization.
Which of these statements are correct?
Hi-Scribble Ltd designs and manufactures pens for a worldwide market. Keith works on one of the production lines and has been told by his team leader that the company is running a project to improve the quality and production rate of the manufacturing line. Keith starts work and notices Diane from the project team visiting every 20 minutes and writing something on her notepad. This happens even when Keith is on his break and sat in the canteen.
Which elicitation method is Diane using?
Ethan, Emma and Jitesh are all members of a team that aims to produce a new expenses approval system for their organisation. Ethan has been sharing his ideas after a recent requirements review. He has applied his expert knowledge of Human Resources (HR) to suggest some potential adjustments to the requirements set, which he feels will make the project more effective. He has agreed to take these ideas back to his HR teams to confirm them. Once the requirements are confirmed, they will go to Jitesh for sign-off.
The whole team has been discussing a potential issue regarding the dates for introducing the new system. Emma has agreed to schedule some time with Jitesh to propose and agree with him her detailed plan for the corrective action they need to reduce the current project slippage.
Based on the scenario above, which of the following represents the roles of Ethan, Emma and Jitesh?
Spicer, an herbs and spices company, is building a new website to grow its business online. A meeting is taking place to prioritize the requirements for inclusion in the first release of the website, which will take place in July. The second release of the website is planned for September.
Miranda, the company buyer is the owner for a requirement that states: 'The system shall provide screens for adding new products'. Miranda informs the meeting that new products are added to the system every three months and that she needs this functionality to be in place before the system goes live. In her view, it is a mandatory requirement.
Peter, who is developing the system, has stated that he can do a one-off upload of all the products into the database ready for launch in July, meaning that the website can initially go live without the 'add new product' functionality.
What priority is Miranda's requirement for the July release?
A business analyst has been working with stakeholders to produce user stories relating to a new high street shopping experience.
The following user stories have been identified:
(a) As the product team lead, I want to be able to price all items as
they arrive in the warehouse.
(b) As a department manager, I want to view the number of items sold to inform my product placement planning.
(c) As the online experience manager, I want to know who is using the
website from overseas locations.
(d) As the chief technology officer, I want to ensure the best possible experience for all our customers.
(e) As a customer, I want quick delivery, so I can receive an item
within one working day of it being released instore.
Which of these include ALL the required elements of a user story?