What would prevent a program manager from completing program closure once a program has been completed?
A small regional utility closes a customer rewards program and transitions it to operations The executive sponsor and program manager are concerned about the impact on benefits realization The program manager assures the executive sponsor that any corrective actions will be included in the next phase.
What should the program manager do to ensure a successful transition?
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next"?