FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. CompTIA Certification
  3. PK0-005 Exam
  4. CompTIA.PK0-005.v2024-05-07.q125 Dumps
  • ««
  • «
  • …
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • …
  • »
  • »»
Download Now

Question 76

While managing a project, a PM is assigned to work on a second project. The second project becomes more
complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed
previously in the organization. Which of the following actions should the PM take?

Correct Answer: D
The project manager should contact the project management office (PMO) for assistance after learning that a
similarly time-consuming project was executed previously in the organization. A PMO is a department or
group within an organization that provides centralized guidance, governance, standards, best practices,
resources, and oversight for project management activities. A PMO can help the project manager by providing
access to historical data, lessons learned, templates, tools, methodologies, and expertise from previous projects
that can be useful for planning and executing the current project.
insert code

Question 77

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Correct Answer: D
A milestone chart is a tool that shows the key events or deliverables of a project along a timeline12. A milestone chart is useful for tracking the progress of a project that has technical tasks and requires a SME's knowledge, because it can provide a high-level overview of the project status, without getting into the details of each task or activity34. A milestone chart can help the PM and the project lead communicate the project achievements, challenges, and expectations to the stakeholders, and also identify any potential risks or delays that may affect the project completion56. A milestone chart is better than the other options because:
A Gantt chart is a tool that shows the tasks, dependencies, durations, and resources of a project along a timeline7. A Gantt chart is more detailed and complex than a milestone chart, and may not be suitable for providing high-level updates to the stakeholders8.
A project organization chart is a tool that shows the roles, responsibilities, and reporting relationships of the project team members and other stakeholders9. A project organization chart is not a tool for tracking project data, but rather for defining the project structure and authority10.
A Program Evaluation Review Technique (PERT) chart is a tool that shows the tasks, dependencies, and critical path of a project along a network diagram. A PERT chart is more focused on the sequence and timing of the project tasks, and may not capture the key milestones or deliverables of the project.
References = CompTIA Project+ Certification Study Guide, CompTIA Project+ Certification Exam Objectives, What is a Milestone Chart?1, How to Create a Milestone Chart in Excel in 3 Steps2, Milestone Chart: The Easiest Way to Track Project Milestones3, How to Use Milestones in Project Management4, What is a Gantt Chart?5, Gantt Chart vs Milestone Chart: What's the Difference?6, What is a Project Organization Chart?7, How to Create a Project Organization Chart8, What is a PERT Chart?9, PERT Chart vs Gantt Chart:
What's the Difference?10
insert code

Question 78

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Correct Answer: B
Explanation
The RACI (Responsible, Accountable, Consulted, Informed) matrix is used to document which resources are responsible for which tasks. The RACI matrix is a tool that helps to clarify roles and responsibilities on a project. It assigns a level of responsibility to each resource involved in the project. References: CompTIA Project+ Study Guide Section 3.4.
The project manager should use a RACI matrix to document which resources are responsible for which tasks.
A RACI matrix is a type of responsibility assignment matrix (RAM) that plots the roles and responsibilities of resources on a project team. RACI stands for Responsible, Accountable, Consulted, and Informed. A RACI matrix can help to clarify who does what on a project, avoid confusion and duplication of work, and improve communication and collaboration among team members.
insert code

Question 79

A project manager has been assigned to a new project. During the planning phase, the project manager needs
to get an understanding of the purpose of the project. Which of the following should the project manager do?

Correct Answer: C
The project manager should review existing artifacts to get an understanding of the purpose of the project.
Existing artifacts are documents or records that provide information about the project background, context,
scope, objectives, requirements, stakeholders, and deliverables. They may include documents such as project
proposal, project charter, business case, feasibility study, statement of work (SOW), or contract. Reviewing
existing artifacts can help to clarify the project vision and expectations and provide a basis for planning and
executing the project.
insert code

Question 80

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

Correct Answer: B
Application deployment typically involves making a software application available for use, often involving downtime or unavailability of the application. The description of the project manager notifying users about the application being unavailable for a certain period aligns with standard practices during deployment phases. The other options, such as rollback plans, validation checks, and maintenance window schedules, although important, do not directly indicate the action of making an application available for use, as described in the scenario.
insert code
  • ««
  • «
  • …
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download CompTIA.PK0-005.v2024-05-07.q125 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.