Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?
Which is a purpose of a Lessons Log?
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?