FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. IIA Certification
  3. IIA-CIA-Part3 Exam
  4. IIA.IIA-CIA-Part3.v2025-01-02.q249 Dumps
  • ««
  • «
  • …
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • …
  • »
  • »»
Download Now

Question 126

The following forms of short-term borrowing are available to an entity: Floating lien Factoring Revolving credit Chattel mortgages Bankers' acceptances . Lines of credit Commercial paper
The forms of short-term borrowing that are unsecured credit are:

Correct Answer: D
An unsecured loan is a loan made by a bank based on credit information about the borrower and the ability of the borrower to repay the obligation. The loan is not secured by collateral, but is made on the signature of the borrower. Unsecured credit is not backed by collateral. Revolving credit bankers' acceptances, lines of credit, and commercial paper are all unsecured means of borrowing. A chattel mortgage is a loan secured by personal property movable property such as equipment or livestock). A floating lien is also secured by property, such as inventory, the composition of which may be constantly changing. Factoring is a form of financing in which receivables serve as security.
insert code

Question 127

The following information and diagram apply to a project:

The earliest completion time for the project is:

Correct Answer: C
The two paths through the network are A-C-E (5+4 + 6= 15days) and B-D-E (3 + 2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.
insert code

Question 128

According to the International Professional Practices Framework, internal auditors who are assessing the adequacy of organizational risk management processes should not:

Correct Answer: D
insert code

Question 129

Based solely on the cost figures presented, the cost of developing the computer application will be:

Correct Answer: A
Development cost equals the cost of the outside contractor plus the costs for hardware and supplies. Computer charges are transfer prices and do not require additional expenditures, given idle capacity. The relevant cost of supplies is US $300 $500 -$200 cost if the software are is purchased). The contractor's use of an otherwise idle office is not relevant. Thus, the relevant cost of development is US $25,500 [[1 .000 hours x $22 hourly cost of the contractor) * $3,200 hardware purchases * $300 incremental cost of supplies]. This amount is US $3,500 less than the US $29,000 cost of purchase. A systems analyst's work on the new software is not relevant. It is part of the regular workload.
Topic 6, Volume F
insert code

Question 130

IAS 34, interim Financial Reporting, provides guidelines for interim reporting stating that enterprises:

Correct Answer: A
Essentially the same reporting methods should be used for interim and annual financial statements. However, the preparation of interim financial reports ordinarily requires a greater use of estimates. For example. IAS 34 states that complete inventory-taking and valuation may not be required at interim dates. Estimates based on sales margins may suffice. Copper Co. had the pre-closing trial balance at December 31 shown below. Additional information: The balance of opening inventory was US $140,000. The long term debt pays interest at a rate of 10% per annum, payable every 12 months. The debt was issued on July 1 of the current year and originally had 5 years to maturity. The assets classified as property, plant, and equipment have a 10-year estimated useful life and were 1 year old at the start of the current year Straight-line depreciation is used.
insert code
  • ««
  • «
  • …
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download IIA.IIA-CIA-Part3.v2025-01-02.q249 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2025 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.