FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. IIBA Certification
  3. CBAP Exam
  4. IIBA.CBAP.v2024-01-19.q463 Dumps
  • ««
  • «
  • …
  • 68
  • 69
  • 70
  • 71
  • 72
  • 73
  • 74
  • 75
  • 76
  • 77
  • …
  • »
  • »»
Download Now

Question 358

There are 50 stakeholders in the current project. How many communication channels exist in this project?

Correct Answer: A
insert code

Question 359

Your organization completes software development for other companies as its core business. Management would like to streamline the requirements gathering processes as many of the projects your company do are similar in nature.
What approach could you as a business analyst do to help streamline the requirements gathering process for your organization?

Correct Answer: D
insert code

Question 360

A business analyst (BA) was presenting requirements to all stakeholders, after having reviewed, structured and organized the requirements. The requirements were being presented in the form of multi layered business process models, using standard notations with proper sequencing of tasks. During the presentation, the project manager points out a few of the missing, inconsistent, and contradictory requirements.
What did the BA fail to perform?

Correct Answer: D
Explanation
Completeness is one of the characteristics of good requirements, along with clarity, consistency, correctness, feasibility, testability, traceability, and prioritization. Completeness means that the requirements specify everything that is necessary and relevant for the solution, and that there are no gaps, omissions, or ambiguities in the requirements. A BA can ensure completeness by using various techniques, such as:
Reviewing the requirements with stakeholders and subject matter experts to verify that they cover all the business needs and objectives, and that they are aligned with the solution scope and vision Validating the requirements against the business case, the project charter, and other relevant documents to confirm that they are consistent and coherent with the project goals and deliverables Analyzing the requirements for dependencies, assumptions, constraints, risks, and issues, and documenting them appropriately Using models, diagrams, and prototypes to illustrate the requirements and identify any missing or unclear aspects Applying quality standards and criteria to evaluate the requirements and ensure that they meet the expectations and requirements of the stakeholders By ensuring completeness, a BA can avoid missing, inconsistent, and contradictory requirements that could lead to confusion, errors, rework, delays, and dissatisfaction among the stakeholders.
References:
[BABOK Guide v3], Section 4.5: Specify and Model Requirements, p. 120-121 CBAP / CCBA Certified Business Analysis Study Guide, 2nd Edition, Chapter 4: Requirements Analysis, p. 153-154 Certified Business Analysis Professional (CBAP) Specialization, Course 2: Business Analysis:
Requirements Analysis and Design Definition, Week 1: Requirements Analysis and Design Definition, Video: Characteristics of Good Requirements
insert code

Question 361

As part of identifying an enterprise's capability to adopt a potential solution, a business analyst (BA) is reviewing existing processes and tools within the enterprise for their ability to adapt to a new solution.
Which of the following assessments is the BA performing?

Correct Answer: D
Explanation/Reference: IIBA BABOKv3 (166)
insert code

Question 362

Which of the following is the comparison of planned project results with actual project results?

Correct Answer: A
Explanation/Reference:
Explanation:
insert code
  • ««
  • «
  • …
  • 68
  • 69
  • 70
  • 71
  • 72
  • 73
  • 74
  • 75
  • 76
  • 77
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download IIBA.CBAP.v2024-01-19.q463 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.