FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. IIBA Certification
  3. CCBA Exam
  4. IIBA.CCBA.v2022-08-03.q164 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 6

You are the business analyst for your organization. You're considering if you should make a solution or purchase it from a vendor. If your team creates the solution, it will cost $286,000 and will cost $2,400 per month to support. The vendor's solution, however, will cost $239,000 and will cost $2,850 per month to support. How long will you need to use your in-house solution to be more cost effective than the vendor's proposed solution?

Correct Answer: A
Explanation
In 105 months, your solution will equate to the cost savings offered by the vendor. In other words, if your solution will be kept longer than
105 months, it's best to use your solution. You can find this solution by first finding the difference of the build and buy costs, which is $47,000. Next, find the difference of the monthly costs, which is only $450. You'll then divide $47,000 by $450 for an answer of 104.4 months, or for this answer, 105 months.
Answer C is incorrect. 64 months is not the correct calculation to this scenario.
Answer B is incorrect. 32 months is not the correct calculation to this scenario.
Answer D is incorrect. 19 months is not the correct calculation to this scenario.
insert code

Question 7

You are hired as a contract project manager for Dreams Unlimited Inc. The project involves setting up ten servers and fifty client computers on the network. From past experience, you know it takes around fifteen hours to install, test, and finalize a server, while it takes only ten hours for a client. You consider these data for making an estimate of schedule of the task. Which of the following estimation techniques has been used?

Correct Answer: A
insert code

Question 8

Enterprise analysis creates just five outputs. Which one of the following is an output of the enterprise analysis tasks?

Correct Answer: C
insert code

Question 9

A business analyst in her organization has identified all of the terminology of the solution, the acronyms the organization will use, and the nomenclature of her department where the endeavor will take place. Where should all of this information actually be stored?

Correct Answer: A
insert code

Question 10

Kendra is the business analyst for her organization. She's working with the project manager and the project sponsor to discuss the current requirements. Kendra believes it's important for the project manager to first implement the requirements with the highest amount of risks. Is this a good idea?

Correct Answer: B
Explanation
It's often best to implement the most risky requirements first in the project. If the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.
Answer A is incorrect. It's not the best idea to implement the lowest risk requirements first.
Answer C is incorrect. Implementing the highest risk requirements last could cause all of the prior work to be
worthless if the risky requirements fail.
Answer D is incorrect. This choice is tempting, but the best reason is the financial consideration of the risky
event in the project.
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download IIBA.CCBA.v2022-08-03.q164 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.