FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CGEIT Exam
  4. ISACA.CGEIT.v2024-05-21.q447 Dumps
  • ««
  • «
  • …
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • …
  • »
  • »»
Download Now

Question 221

Which of the following outsourcing defines the performance objectives reached by negotiation between the user and the provider of a service, or between an outsourcer and an organization?

Correct Answer: B
insert code

Question 222

An enterprise is experiencing a pattern of sensitive data breaches. While each breach has been successfully remediated, leadership is concerned about recurrence. What should the leadership team do FIRST?

Correct Answer: C
insert code

Question 223

An enterprise has a large backlog of IT projects. The current strategy is to execute projects as they are submitted, but executive management does not believe this method is optimal. Which of the following is the MOST important action to address this concern?

Correct Answer: B
insert code

Question 224

Which of the following provides the BEST evidence of effective IT governance?

Correct Answer: A
insert code

Question 225

An IT investment review board wants to ensure that IT will be able to support business initiatives. Each initiative is comprised of several interrelated IT projects. Which of the following would help ensure that the initiatives meet their goals?

Correct Answer: C
Portfolio management is the process of selecting, prioritizing, and managing a collection of projects, programs, and initiatives that align with the strategic goals and objectives of an organization. Portfolio management can help to ensure that the IT initiatives meet their goals, by providing a holistic and integrated view of the IT investments, resources, and outcomes. Portfolio management can also help to optimize the value and benefits of the IT initiatives, by balancing the risks, costs, and dependencies among them. Portfolio management can also help to monitor and control the performance and progress of the IT initiatives, by using metrics, indicators, and reports123. : What is Portfolio Management? Definition & Examples. A Guide to IT Portfolio Management | Adobe Workfront. IT Portfolio Management: Importance, How-To Steps and Tips.
insert code
  • ««
  • «
  • …
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CGEIT.v2024-05-21.q447 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.