FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CISM Exam
  4. ISACA.CISM.v2023-03-13.q122 Dumps
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
Download Now

Question 41

When collecting admissible evidence, which of the following is the MOST important requirement?

Correct Answer: D
Explanation
The most important requirement when collecting admissible evidence is the chain of custody. The chain of custody is a documented record of who had control of the evidence at any given time, from the point of collection until the evidence is presented in court. This is important in order to ensure the evidence can be authenticated and is not subject to tampering or any other form of interference. Other important considerations include need to know, preserving audit logs, and due diligence.
insert code

Question 42

Which of the following is the BEST method to protect against emerging advanced persistent threat (APT) actors?

Correct Answer: D
insert code

Question 43

Which of the following is the MOST important reason for obtaining input from risk owners when implementing controls?

Correct Answer: C
Explanation
According to the Certified Information Security Manager (CISM) Study Manual, risk owners are responsible for managing a risk, including taking corrective action to reduce the risk to an acceptable level. When implementing controls, it is essential to obtain input from risk owners to ensure that the controls are effective in managing the risk to an acceptable level.
By obtaining input from risk owners, the organization can ensure that the controls are tailored to the specific risks and are effective in reducing the risk to an acceptable level. This can help to minimize the impact of the risk on the organization and reduce the potential for financial or reputational damage.
insert code

Question 44

The MOST appropriate time to conduct a disaster recovery test would be after:

Correct Answer: D
insert code

Question 45

Which of the following activities is designed to handle a control failure that leads to a breach?

Correct Answer: D
insert code
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CISM.v2023-03-13.q122 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.