FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 103
  • 104
  • 105
  • 106
  • 107
  • 108
  • 109
  • 110
  • 111
  • 112
  • …
  • »
  • »»
Download Now

Question 531

Which of the following should be the PRIMARY focus of an IT risk awareness program?

Correct Answer: A
insert code

Question 532

Which of the following would be MOST useful when measuring the progress of a risk response action plan?

Correct Answer: C
Section: Volume D
insert code

Question 533

You are the project manager of GHT project. You and your team have developed risk responses for those risks with the highest threat to or best opportunity for the project objectives. What are the immediate steps you should follow, after planning for risk response process? Each correct answer represents a complete solution. Choose three.

Correct Answer: A,C,D,E
is incorrect. Controls are implemented in the latter stage of risk response process. It is not immediate task after the planning of risk response process, as updating of several documents is done first. The purpose of the Plan Risk Responses process is to develop risk responses for those risks with the highest threat to or best opportunity for the project objectives. The Plan Risk Responses process has four outputs: Risk register updates Risk-related contract decisions Project management plan updates Project document updates
insert code

Question 534

An organization is measuring the effectiveness of its change management program to reduce the number of unplanned production changes. Which of the following would be the BEST metric to determine if the program is performing as expected?

Correct Answer: C
insert code

Question 535

Which of the following is the MOST comprehensive resource for prioritizing the implementation of information systems controls?

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 103
  • 104
  • 105
  • 106
  • 107
  • 108
  • 109
  • 110
  • 111
  • 112
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.