FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 113
  • 114
  • 115
  • 116
  • 117
  • 118
  • 119
  • 120
  • 121
  • 122
  • …
  • »
  • »»
Download Now

Question 581

While developing obscure risk scenarios, what are the requirements of the enterprise?
Each correct answer represents a part of the solution. Choose two.

Correct Answer: B,D
Explanation/Reference:
Explanation:
The enterprise must consider risk that has not yet occurred and should develop scenarios around unlikely, obscure or non-historical events.
Such scenarios can be developed by considering two things:
Visibility

Recognition

For the fulfillment of this task enterprise must:

Be in a position that it can observe anything going wrong

Have the capability to recognize an observed event as something wrong

Incorrect Answers:
A, C: These are not the direct requirements for developing obscure risk scenarios, like curing risk events comes under process of risk management. Hence capability of curing risk event does not lay any impact on the process of development of risk scenarios.
insert code

Question 582

Which of the following are risk components of the COSO ERM framework?
Each correct answer represents a complete solution. Choose three.

Correct Answer: A,B,D
Explanation/Reference:
Explanation:
The risk components defined by the COSO ERM are internal environment, objective settings, event identification, risk assessment, risk response, control objectives, information and communication, and monitoring.
Incorrect Answers:
C: Business continuity is not considered as risk component within the ERM framework.
insert code

Question 583

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via. email every week. You have agreed and send reports every Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Correct Answer: C
is incorrect. Communications management is the execution of the communications management plan. Answer:D is incorrect. The project change control process not valid as it's the parent of the integrated change control process, which is more accurate for this option A is incorrect. Configuration management is the documentation and control of the product's features and functions.
insert code

Question 584

Shawn is the project manager of the HWT project. In this project Shawn's team reports that they have found a way to complete the project work cheaply than what was originally estimated earlier. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes the project management plan accordingly. What type of risk response had been used by him?

Correct Answer: C
is incorrect. Accepting is a risk response that is appropriate for positive or negative risk events. It does not pursue the risk, but documents the event and allows the risk to happen. Often acceptance is used for low probability and low impact risk events. Answer:A is incorrect. To avoid a risk means to evade it altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event. Answer:D is incorrect. Enhancing is a positive risk response that aims to increase the probability and/or impact of the risk event.
insert code

Question 585

A risk practitioner has identified that the organization's secondary data center does not provide redundancy for a critical application. Who should have the authority to accept the associated risk?

Correct Answer: B
Section: Volume D
insert code
  • ««
  • «
  • …
  • 113
  • 114
  • 115
  • 116
  • 117
  • 118
  • 119
  • 120
  • 121
  • 122
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.