FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 128
  • 129
  • 130
  • 131
  • 132
  • 133
  • 134
  • 135
  • 136
  • 137
  • …
  • »
  • »»
Download Now

Question 656

Which among the following is the MOST crucial part of risk management process?

Correct Answer: A
Section: Volume C
Explanation:
Risk communication is a critical part in the risk management process. People are naturally uncomfortable talking about risk and tend to put off admitting that risk is involved and communicating about issues; incidents; and; eventually, even crises.
If risk is to be managed and mitigated, it must first be discussed and effectively communicated throughout an enterprise.
Incorrect Answers:
B: Auditing is done to test the overall risk management process and the planned risk responses. So it is the very last phase after completion of risk management process.
C: Risk monitoring is the last phase to complete risk management process, and for proper management of risk it should be communicated properly. Hence risk communication is the most crucial step.
D: Risk mitigation is one of the phases of risk management process for effective mitigation of risk it should be first communicated throughout an enterprise.
insert code

Question 657

A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?

Correct Answer: C
is incorrect. Risks that have a low probability and a low impact may go on the low-level risk watch-list. Answer:B is incorrect. This is a risk event and should be recorded in the risk register. Answer:A is incorrect. Control management charts are not the place where risk events are recorded.
insert code

Question 658

Which of the following would be a risk practitioner's BEST recommendation to help ensure cyber risk is assessed and reflected in the enterprise-level risk profile?

Correct Answer: C
Section: Volume D
insert code

Question 659

You are the project manager of your project. You have to analyze various project risks. You have opted for quantitative analysis instead of qualitative risk analysis. What is the MOST significant drawback of using quantitative analysis over qualitative risk analysis?

Correct Answer: B
Section: Volume B
Explanation:
Quantitative risk analysis is generally more complex and thus is costlier than qualitative risk analysis.
Incorrect Answers:
A: Neither of the two risk analysis methods is fully objective. Qualitative method subjectively assigns high, medium and low frequency and impact categories to a specific risk, whereas quantitative method subjectivity expressed in mathematical "weights".
C: To be effective, both processes require personnel who have a good understanding of the business. So there is equal requirement of skilled personnel in both.
D: Quantitative analysis generally has a better buy-in than qualitative analysis to the point where it can cause over-reliance on the results. Hence this option is not correct.
insert code

Question 660

Which of the following BEST describes the utility of a risk?

Correct Answer: D
Section: Volume A
Explanation:
The utility of the risk describes the usefulness of a particular risk to an individual. Moreover, the same risk can be utilized by two individuals in different ways. Financial outcomes are one of the methods for measuring potential value for taking a risk. For example, if the individual's economic wealth increases, the potential utility of the risk will decrease.
Incorrect Answers:
A: Determining financial incentive is one of the method to measure the potential value for taking a risk, but it is not the valid definition for utility of risk.
B: It is not the valid definition.
C: It is not the valid definition.
insert code
  • ««
  • «
  • …
  • 128
  • 129
  • 130
  • 131
  • 132
  • 133
  • 134
  • 135
  • 136
  • 137
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.