FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 150
  • 151
  • 152
  • 153
  • 154
  • 155
  • 156
  • 157
  • 158
  • 159
  • …
  • »
  • »»
Download Now

Question 766

Judy has identified a risk event in her project that will have a high probability and a high impact. Based on the requirements of the project, Judy has asked to change the project scope to remove the associated requirement and the associated risk. What type of risk response is this?

Correct Answer: C
Section: Volume C
Explanation
Explanation:
Risk avoidance involves changing the project management plan to eliminate the threat entirely. The project manager may also isolate the project objectives from the risk's impact or change the objective that is in jeopardy. Examples of this include extending the schedule, changing the strategy, or reducing the scope. The most radical avoidance strategy is to shut down the project entirely. Some risks that arise early in the project can be avoided by clarifying requirements, obtaining information, improving communication, or acquiring expertise.
Incorrect Answers:
A: Exploit risk response is used for positive risk or opportunity, not for negative risk.
B: This risk response does require a change request, in some instances, but it's the avoidance risk response and not just a change request.
D: Transference allows the risk to be transferred, not removed from the project, to a third party. Transference usually requires a contractual relationship with the third party.
insert code

Question 767

You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?

Correct Answer: C
is incorrect. Benchmarking compares any two items, such as materials, vendors, or
resources.
insert code

Question 768

Which of the following is the BEST key performance indicator (KPI) to measure the effectiveness of an antivirus program?

Correct Answer: A
insert code

Question 769

In which of the following risk management capability maturity levels risk appetite and tolerance are applied only during episodic risk assessments?

Correct Answer: D
Explanation/Reference:
Explanation:
An enterprise's risk management capability maturity level is 1 when:
There is an understanding that risk is important and needs to be managed, but it is viewed as a

technical issue and the business primarily considers the downside of IT risk.
Any risk identification criteria vary widely across the enterprise.

Risk appetite and tolerance are applied only during episodic risk assessments.

Enterprise risk policies and standards are incomplete and/or reflect only external requirements and lack

defensible rationale and enforcement mechanisms.
Risk management skills exist on an ad hoc basis, but are not actively developed.

Ad hoc inventories of controls that are unrelated to risk are dispersed across desktop applications.

Incorrect Answers:
A: In level 3 of risk management capability maturity model, local tolerances drive the enterprise risk tolerance.
B: In level 2 of risk management capability maturity model, risk tolerance is set locally and may be difficult to aggregate.
C: In level 4 of risk management capability maturity model, business risk tolerance is reflected by enterprise policies and standards reflect.
insert code

Question 770

The BEST way to obtain senior management support for investment in a control implementation would be to articulate the reduction in:

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 150
  • 151
  • 152
  • 153
  • 154
  • 155
  • 156
  • 157
  • 158
  • 159
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.