FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 51
  • 52
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60
  • …
  • »
  • »»
Download Now

Question 271

The head of a business operations department asks to review the entire IT risk register. Which of the following would be the risk manager s BEST approach to this request before sharing the register?

Correct Answer: B
insert code

Question 272

Which of the following is the PRIMARY objective for automating controls?

Correct Answer: C
insert code

Question 273

Wendy has identified a risk event in her project that has an impact of $75,000 and a 60 percent chance of happening. Through research, her project team learns that the risk impact can actually be reduced to just $15,000 with only a ten percent chance of occurring. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this?

Correct Answer: A
is incorrect. Avoidance changes the project plan to avoid the risk altogether. Answer: C is incorrect. Transference requires shifting some or all of the negative impacts of a threat, along with the ownership of the response, to a third party. Transferring the risk simply gives another party the responsibility for its management-it does not eliminate it. Transferring the liability for a risk is most effective in dealing with financial risk exposure. Risk transference nearly always involves payment of a risk premium to the party taking on the risk. Answer: D is incorrect. Enhancing is actually a positive risk response. This strategy is used to increase the probability and/or the positive impact of an opportunity. Identifying and maximizing the key drivers of these positive-impact risks may increase the probability of their occurrence.
insert code

Question 274

Within the three lines of defense model, the accountability for the system of internal control resides with:

Correct Answer: C
insert code

Question 275

A risk owner has accepted a high-impact risk because the control was adversely affecting process efficiency.
Before updating the risk register, it is MOST important for the risk practitioner to:

Correct Answer: B
insert code
  • ««
  • «
  • …
  • 51
  • 52
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.