FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2024-01-06.q281 Dumps
  • ««
  • «
  • …
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • …
  • »
  • »»
Download Now

Question 36

Which of the following will BEST mitigate the risk associated with IT and business misalignment?

Correct Answer: B
insert code

Question 37

Which of the following is the MOST important outcome of reviewing the risk management process?

Correct Answer: B
Section: Volume D
insert code

Question 38

You are the project manager of GFT project. Your project involves the use of electrical motor. It was stated in its specification that if its temperature would increase to 500 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. If the machine overheats even once it will delay the project's arrival date. So to prevent this you have decided while creating response that if the temperature of the machine reach 450, the machine will be paused for at least an hour so as to normalize its temperature. This temperature of 450 degree is referred to as?

Correct Answer: B
Explanation/Reference:
Explanation:
A risk trigger is a warning sign or condition that a risk event is about to happen. Here the warning temperature is 450 degree Fahrenheit, therefore it is referred as risk trigger.
Incorrect Answers:
A: Risk identification is the process of the identifying the risks. This process identifies the risk events that could affect the project adversely or would act as opportunity.
C: Here risk event is 500 degree temperature, as when machine reaches this temperature it should have to be shut-down for 48 hours, which in turn will laid a great impact on the working of project.
D: Risk response here is shutting off of machine when its temperature reaches 450 degree Fahrenheit, so as to prevent the occurring of risk event.
insert code

Question 39

In an organization dependent on data analytics to drive decision-making, which of the following would BEST help to minimize the risk associated with inaccurate data?

Correct Answer: A
Section: Volume D
insert code

Question 40

Your project is an agricultural-based project that deals with plant irrigation systems. You have
discovered a byproduct in your project that your organization could use to make a profit. If your organization seizes this opportunity it would be an example of what risk response?

Correct Answer: D,E
is incorrect. Opportunistic is not a valid risk response. Answer: B is incorrect. This is an example of a positive risk, but positive is not a risk response. Answer: A is incorrect. Enhancing is a positive risk response that describes actions taken to increase the odds of a risk event to happen.
insert code
  • ««
  • «
  • …
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2024-01-06.q281 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.