FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2024-06-22.q384 Dumps
  • ««
  • «
  • …
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • …
  • »
  • »»
Download Now

Question 171

Which of the following BEST provides an early warning that network access of terminated employees is not being revoked in accordance with the service level agreement (SLA)?

Correct Answer: A
Section: Volume D
insert code

Question 172

Who should be responsible for implementing and maintaining security controls?

Correct Answer: A
Section: Volume D
insert code

Question 173

Which of the following is the BEST indication of a mature organizational risk culture?

Correct Answer: C
insert code

Question 174

Mortality tables are based on what mathematical activity?
Each correct answer represents a complete solution. Choose three.

Correct Answer: A,B,D,E
is incorrect. Impact is used to identify the magnitude of identified risks. The risk leads to
some type of loss. However, instead of quantifying the loss as a dollar value, an impact assessment could use words such as Low, Medium, or High. Hence it is not mathematical.
insert code

Question 175

Which one of the following is the only output for the qualitative risk analysis process?

Correct Answer: B
Section: Volume B
Explanation:
Risk register update is the only output of the choices presented for the qualitative risk analysis process. The four inputs for the qualitative risk analysis process are the risk register, risk management plan, project scope statement, and organizational process assets. The output of perform qualitative risk analysis process is Risk Register Updates. Risk register is updated with the information from perform qualitative risk analysis and the updated risk register is included in the project documents. Updates include the following important elements:
* Relative ranking or priority list of project risks
* Risks grouped by categories
* Causes of risk or project areas requiring particular attention
* List of risks requiring response in the near-term
* List of risks for additional analysis and response
* Watchlist of low priority risks
* Trends in qualitative risk analysis results
Incorrect Answers:
A, C, D: These are not the valid outputs for the qualitative risk analysis process.
insert code
  • ««
  • «
  • …
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2024-06-22.q384 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.