FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2024-06-22.q384 Dumps
  • ««
  • «
  • …
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • 51
  • 52
  • 53
  • …
  • »
  • »»
Download Now

Question 236

An organization is conducting a review of emerging risk. Which of the following is the BEST input for this exercise?

Correct Answer: C
insert code

Question 237

You are the project manager of GHT project. You have identified a risk event on your current project that could save $670,000 in project costs if it occurs. Your organization is considering hiring a vendor to help establish proper project management techniques in order to assure it realizes these savings. Which of the following statements is TRUE for this risk event?

Correct Answer: D,E,F,G
is incorrect. The risk event is mitigated when it has negative impacts. But here it is
positive consequences (i.e., saving), therefore it is not mitigated.
insert code

Question 238

What are the PRIMARY requirements for developing risk scenarios?
Each correct answer represents a part of the solution. Choose two.

Correct Answer: A,B
Explanation/Reference:
Explanation:
Creating a scenario requires determination of the value of an asset or a business process at risk and the potential threats and vulnerabilities that could cause loss. The risk scenario should be assessed for relevance and realism, and then entered into the risk register if found to be relevant.
In practice following steps are involved in risk scenario development:
First determine manageable set of scenarios, which include:

Frequently occurring scenarios in the industry or product area.

Scenarios representing threat sources that are increasing in count or severity level.

Scenarios involving legal and regulatory requirements applicable to the business.

After determining manageable risk scenarios, perform a validation against the business objectives of

the entity.
Based on this validation, refine the selected scenarios and then detail them to a level in line with the

criticality of the entity.
Lower down the number of scenarios to a manageable set. Manageable does not signify a fixed

number, but should be in line with the overall importance and criticality of the unit.
Risk factors kept in a register so that they can be reevaluated in the next iteration and included for

detailed analysis if they have become relevant at that time.
Risk factors kept in a register so that they can be reevaluated in the next iteration and included for

detailed analysis if they have become relevant at that time.
Include an unspecified event in the scenarios, that is, address an incident not covered by other

scenarios.
Incorrect Answers:
C, D: Determination of actors and threat type are not the primary requirements for developing risk scenarios, but are the components that are determined during risk scenario development.
insert code

Question 239

When it appears that a project risk is going to happen, what is this term called?

Correct Answer: C
Section: Volume C
Explanation:
A trigger is a warning sign or a condition that a risk event is likely to occur within the project.
Incorrect Answers:
A: Issues are events that come about as a result of risk events. Risks become issues only after they have actually occurred.
B: A contingency response is a pre-planned response for a risk event, such as a rollback plan.
D: A threshold is a limit that the risk passes to actually become an issue in the project.
insert code

Question 240

Which of the following would require updates to an organization's IT risk register?

Correct Answer: A
Section: Volume D
insert code
  • ««
  • «
  • …
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • 51
  • 52
  • 53
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2024-06-22.q384 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.