FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2024-06-22.q384 Dumps
  • ««
  • «
  • …
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • 69
  • 70
  • …
  • »
  • »»
Download Now

Question 321

Which of the following is the first MOST step in the risk assessment process?

Correct Answer: A
Explanation/Reference:
Explanation:
Asset identification is the most crucial and first step in the risk assessment process. Risk identification, assessment and evaluation (analysis) should always be clearly aligned to assets. Assets can be people, processes, infrastructure, information or applications.
insert code

Question 322

What can be determined from the risk scenario chart?

Correct Answer: B
insert code

Question 323

Which of the following risk register updates is MOST important for senior management to review?

Correct Answer: D
Section: Volume D
insert code

Question 324

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

Correct Answer: A
Explanation/Reference:
Explanation:
The Identified risks and potential responses are documented in the risk register. A risk register is an inventory of risks and exposure associated with those risks. Risks are commonly found in project management practices, and provide information to identify, analyze, and manage risks. Typically a risk register contains:
A description of the risk

The impact should this event actually occur

The probability of its occurrence

Risk Score (the multiplication of Probability and Impact)

A summary of the planned response should the event occur

A summary of the mitigation (the actions taken in advance to reduce the probability and/or impact of the

event)
Ranking of risks by Risk Score so as to highlight the highest priority risks to all involved.

Incorrect Answers:
B: This is not a valid choice for this question
C: The project management plan is the parent of the risk management plan, but the best choice is the risk register.
D: The risk management plan is an input to the risk response planning, but it is not the best choice for this question
insert code

Question 325

Which of the following is the GREATEST benefit to an organization when updates to the risk register are made promptly after the completion of a risk assessment?

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • 69
  • 70
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2024-06-22.q384 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.