FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISQI Certification
  3. CTAL-TM-001 Exam
  4. ISQI.CTAL-TM-001.v2025-10-23.q104 Dumps
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
Download Now

Question 41

Which three of the following would be considered a good mix of technical and interpersonal skills (hard and soft), for a test team leader?
a. Ability to compliment a developer.
b. Presenting information regarding a test project progress to stakeholders c. Using a configuration management tool.
d. Ability to read a development coding language
e. Assessing a failure and documenting it correctly.

Correct Answer: D
insert code

Question 42

What occurs In the retrospective closing?

Correct Answer: C
Purpose of Retrospectives:
Retrospectives are team meetings aimed at reflecting on the work process to identify what went well (strengths) and areas that can be improved (opportunities).
This aligns with continuous process improvement practices.
Evaluation of Options:
A (Everyone shakes hands) is trivial and not a core activity.
B (Reviewing data collection methods) may be part of broader discussions but is not the primary focus.
C is correct because it directly reflects retrospective goals.
D (Brainstorming solutions) typically occurs in follow-up sessions, not during the retrospective itself.
Reference and Syllabus Alignment:
Retrospective practices are emphasized in "Improving the Test Process" (TM-1.5.4) in the syllabus.
insert code

Question 43

During what step of the Fundamental Test Process should you define the methods to be used to collect test metrics? [1]

Correct Answer: B
The correct answer is B. Planning. This is because test metrics are quantitative measures that are used to monitor and control the test process, and to evaluate the test results and quality. Test metrics should be defined during the planning step of the Fundamental Test Process, which is the activity of establishing the test objectives, scope, approach, resources, schedule, and deliverables. By defining the methods to be used to collect test metrics during the planning step, the test team can ensure that the test metrics are aligned with the test plan and the project goals, and that the data collection process is consistent and efficient. Test Metrics - ISTQB not-for-profit association References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Test Metrics - ISTQB not-for-profit association
insert code

Question 44

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]

Correct Answer: C
The most critical activity of the standard test process for the Test Manager to perform in this scenario is test monitoring and control. This is because test monitoring and control involves measuring and evaluating the test progress, quality, and risks, and taking corrective actions when necessary. Given the aggressive schedule, the unclear requirements, the new technologies, the offshore development team, the limited testing resources, and the high stakeholder expectations, the Test Manager needs to closely monitor and control the testing activities to ensure that the test objectives and exit criteria are met, and that any deviations or issues are identified and resolved in a timely manner. Test Monitoring and Control - ISTQB not-for-profit association Reference: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Test Monitoring and Control - ISTQB not-for-profit association
insert code

Question 45

You are the Test Manager of a risk-based testing effort. You develop the following graph to show residual risk. Assume that "Risks mitigated" represents passed tests and "Risks not mitigated" represents failed tests and other discovered failures.
Which of the following answers best represents what the graph shows? [3]

Correct Answer: C
The graph indicates that a significant portion of risks, 29%, have not been mitigated, which suggests that these are either failed tests or other discovered failures. This level of unmitigated risk puts the project at risk, as it implies that there are still substantial issues that need to be addressed.
References:The ISTQB Advanced Level Test Manager documents outline the importance of risk-based testing and the interpretation of residual risk graphs. These graphs are used to communicate the current status of risk mitigation efforts in the project, and a high percentage of unmitigated risks is a clear indicator of potential problems1.
insert code
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISQI.CTAL-TM-001.v2025-10-23.q104 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.