| Exam Code/Number: | 070-177Join the discussion |
| Exam Name: | TS: Microsoft Project Server 2010, Configuring |
| Certification: | Microsoft |
| Question Number: | 75 |
| Publish Date: | Oct 05, 2026 |
|
Rating
100%
|
|
You have a Project Server 2010 environment. You create a new enterprise task field. You need to create an aggregated pivot analysis of the new enterprise task field. What should you do?
You have a Project Server 2010 environment. You install Project Professional 2010. Your user permissions in Project Server allow you to edit projects in Project Professional. You need to open a project on Project Server in Project Professional. What should you do first?
You have a Project Server 2010 environment. Project managers report that they are not receiving all the timesheet updates that users are submitting. You need to ensure that the project managers always receive task updates when users submit their timesheets. What should you do?
You have a Project Server 2010 environment. You create a custom view to display a list of delayed projects. You need to make sure that only senior managers in your company have access to the custom view. What should you do?
You have a Project Server 2010 environment. You need to configure Project Server to allow members of the maintenance crew to choose their work assignments from a shared list. What should you do?