You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?
John, a team member, will be absent from the team. A new team member, Mary, will take over Johns remaining work. You need to update the project schedule to reflect the change. You also need to retain John's actual work. What should you do?
You need to compare the total work of your project's deliverables against the baseline work. What should you do?
You manage several projects saved on a shared drive. You want to create a critical path relationship between several schedules managed by other project managers. You need to link the project schedules at the task level. You also need to ensure that each project manager can continue to manage their own project. What should you do?
The dates of your project are displayed in the long date format as Wed 09-01-28 12:33. You need to ensure that the dates are displayed as 1/28/09. What should you do?