| Exam Name: | Managing Projects with Microsoft Project 2013 |
| Certification: | Microsoft |
| Question Number: | 110 |
| Publish Date: | Oct 16, 2025 |
|
Rating
100%
|
|
You manage a project by using Project Professional 2013.
A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.
You need to implement a solution to meet the stakeholder's request.
What should you do?
You are a project manager in an organization that uses Project Professional 2013.
You are managing a project, which involves the construction of a new shopping mall. The shopping mall is scheduled to finish by October 21. The mall needs to start operations by October 31. Your sponsor asks you to closely monitor your schedule and informs you that missing the October 21 deadline could jeopardize the October 31 start date.
You are concerned about construction delays, and you want to reduce the time buffer. Your sponsor agrees with this decision.
You need to show the time between the End of Construction and the Grand Opening Day as a time buffer for delays.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)
You are a project manager who uses Project Professional 2013.
A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the Number1 field of your customer's project.
You need to copy the custom fields from your customer's project into your own. You do not want to overwrite your project custom field.
You open both projects.
What should you do next?
You are a project manager who uses Project Professional 2013.
Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week.
You need to set up their calendars to reflect the job-sharing arrangement.
What should you do?
You are a project manager who uses Project Standard 2013.
You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in size.
You need to share this project plan by email with your team and ensure that they can easily access the documents.
What should you do?