You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
-- --
Review the project data after the project managers create the projects.
Send the projects back to the project managers if you find incorrect data so that
they can make the appropriate corrections.
Repeat the data verification process unless the data does not have any errors.
Publish a project only when all of its data is correctly completed.
What should you do?
You are a resource manager and manage a project with Project Server 2013 and Project Professional 2013.
Without notice, one of your key resources decides to take a leave of absence for 30 days.
You need to account for the absent resource and assess how the absence will affect your schedule.
What should you do?
---
You are a program manager in the Project Management Office (PMO) of an organization that is implementing Project Server 2013.
You plan to include five of your organization's departments in the first rollout of Project Server 2013.
You need to develop a project creation process that meets the following requirements:
Each department must have its own Project Site template.
Each department must have its own Project Schedule template.
The project creation process needs to be developed in the least amount of time.
What should you do?
Your company uses Project Server 2013 to evaluate and select projects based on a primary cost constraint, as well as a secondary constraint of internal rate of return (IRR).
Management authorizes a budget and establishes a minimal IRR of 5% to execute any project the following year. Your company has never analyzed constraints other than cost.
As the portfolio analysis expert, you need to recommend a reasonable approach to perform the analysis.
What should you recommend?
You are a project manager in an organization that uses Project Server 2013. You have access to Project Web App (PWA) but no access to Project Professional 2013 for making changes to your schedule.
In your organization, projects begin work after the project sponsor provides funding for the first phase of the project.
You need to take a snapshot of your schedule and make that information available to the Project Management Office (PMO), who will view it in PWA.
What should you do?