A company implements Dynamics 365 for Finance and Operations. You must use functionality in the system for group production runs to prevent downtime and excessive cleaning of the machines on the production line.
You need to set up the system.
Which behaviors should you expect? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.


You are the product manager at a paint manufacturing company. Paint base is produced in 100 gallon batches.
The paint base can be packaged in 1 gallon, 5 gallon, and 10 gallon containers.
You want to use consolidated batch orders for the bulk paint base item. You need to set up the items and formulas to allow for consolidated batch orders.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


You need to modify the production order defaults for the manufacturing execution production order Start process.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.


A company uses Lean manufacturing concepts to produce paper plates redesigned the layout of the warehouse and production floor.
The company's production flow activities no longer match the tasks of the workers Employees use paper and manual communication to complete the tasks.
You need to update the production flows to match their current processes by deactivating the obsolete production flows and creating new ones.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


A customer produces light projection toys for holiday decorations throughout the year.
You must implement Bills of material (BOMs) for the product lifecycle. The solution must meet the following requirements:
You need to create a BOM for each phase.
Which BOM types should you use? To answer, select the appropriate configuration options in the answer area.
NOTE: Each correct selection is worth one point.