Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
1.) Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service
2.) Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell
3.) Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity
4.) Create a service term to tie the purchase agreement to the activity Does this solution meet the goal?
A company produces generic and name-brand paper plates in the same factory using standard costing and using the same Bill of materials and routes to produce both products. The finance and production teams want a way to view individual raw material consumption costs in the ledger. You need to add a production group to the finished good to control postings to the ledger. What should you do?
You manage pricing for a food processing company. The raw materials used by the business is a commodity-traded product and has a changing purchase price.
You must implement the commodity pricing module. You create a pricing template with margin data.
You need to calculate the cost price for the manufactured goods as well as the sales price based on margin standards.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


A pharmaceutical manufacturer uses Process manufacturing.
You are consolidating planned batch orders for a specific medication. The order must cover two weeks of demand. No other items need to be consolidated.
You need to change the coverage group of the items.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


You work for a gem wholesaler that sells raw diamonds. Diamonds are purchased and sold in individual boxes but weighed and inventoried in carats.
You are setting up a catch weight item for diamonds. Each box of diamonds must be tracked by its individual container weight.
You need to set up this item as a full visibility catch weight item.
Which two steps must you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.