A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
A manufacturer uses discreet orders and manually consumes raw material after reporting products as finished.
You are performing an end-of-month closing for remaining picking lists on production orders. You must not be required to consume the full amount of material on production order picking lists as a result of improved production efficiency. When the production manager verifies that no material is left to consume, there are remaining back-ordered amounts.
You need to pick the line item short and eliminate the remaining demand.
What should you do?
You manage pricing for a food processing company. The raw materials used by the business is a commodity-traded product and has a changing purchase price.
You must implement the commodity pricing module. You create a pricing template with margin data.
You need to calculate the cost price for the manufactured goods as well as the sales price based on margin standards.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


A company implements Dynamics 365 Supply Chain Management.
Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:
* Locate a warehouse at the subcontractor building.
* Support picking and shipping activity tracking.
* Associate costs of transporting materials between the locations in the cost of the finished product.
You need to modify the production flow.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to configure each item for plastic manufacturing.
Which production types should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.