A company plans to implement Dynamics 365 for Finance chain Operations.
You need to determine which manufacturing solutions to use.
Which manufacturing solution should you use? To answer, drag the appropriate setting to the correct drop targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.


A company uses warehouse management and manufacturing execution to process their production orders.
You configure the manufacturing execution production order defaults to always consume Bill of materials (BOM) components when an operation step is completed in the job registration terminal. You create a production order. The order is in released status.
You need to process this order all the way through to end status.
Which four actions should you perform in sequence? To answer, check the appropriate actions to the answer area and arrange them in the correct order.

A process manufacturing company is implementing Dynamics 365 for Finance and Operations. The company will use multiple process manufacturing functionalities including by-products.
You need to configure by-product formula allocation methods.
Which methods should you use? To answer, drag the appropriate by-product burden allocation methods to the correct scenarios. Each method may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content NOTE: Each correct selection is worth one point.

A company overstates on-hand raw materials due to the time it takes to post raw materials as consumed when production orders are processed.
All items used to manufacture finished goods must be consumed when a finished good is reported as finished.
You must not change all bill of materials lines to use the option of flushing principal.
You need to ensure that all production orders consume raw materials at Report as finished.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.