A company has a business-critical desktop flow that runs on a single machine. The number of daily runs for the flow has significantly increased recently.
Users report that the time required for the flow to complete is no longer acceptable.
You need to scale the solution.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You design an attended Power Automate desktop flow that updates orders in an older enterprise resource planning (ERP) system.
A warehouse supervisor enters the order status and fulfilment date when an order is fulfilled.
The flow must be installed on a desktop computer in the warehouse and triggered by using a shortcut.
You need to configure the flow to deploy and run.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


You are designing automation processes for a company.
You need to select the appropriate action for each automation scenario.
Which actions should you perform? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.


A developer creates a desktop flow.
You need to debug the flows.
Which debugging tools should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.


You need to configure the RailStatusUpdater cloud flow. What should you do?