FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. CAPM Exam
  4. PMI.CAPM.v2022-04-08.q645 Dumps
  • ««
  • «
  • …
  • 104
  • 105
  • 106
  • 107
  • 108
  • 109
  • 110
  • 111
  • 112
  • 113
  • …
  • »
  • »»
Download Now

Question 536

The project team is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods.
What is the team trying to address?

Correct Answer: C
insert code

Question 537

A new project manager wishes to recommend creating a project management office to senior management.
Which statement would the project manager use to describe the importance of creating the project management office?

Correct Answer: D
Section: Volume E
Explanation/Reference: https://www.theprojectgroup.com/blog/en/why-a-pmo-is-important/
insert code

Question 538

Which of the following are three inputs to the risk register?

Correct Answer: A
insert code

Question 539

The progressive detailing of the project management plan is called:

Correct Answer: B
Section: Volume D
Explanation:
6.2.2.2 Rolling Wave Planning
Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level. It is a form of progressive elaboration.
Therefore, work can exist at various levels of detail depending on where it is in the project life cycle. During early strategic planning, when information is less defined, work packages may be decomposed to the known level of detail. As more is known about the upcoming events in the near term, work packages can be decomposed into activities.
4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes.
Project baselines include, but are not limited to:
Scope baseline (Section 5.4.3.1),

Schedule baseline (Section 6.6.3.1), and

Cost baseline (Section 7.3.3.1).

Subsidiary plans include, but are not limited to:
Scope management plan (Section 5.1.3.1),

Requirements management plan (Section 5.1.3.2),

Schedule management plan (Section 6.1.3.1),

Cost management plan (Section 7.1.3.1),

Quality management plan (Section 8.1.3.1),

Process improvement plan (Section 8.1.3.2),

Human resource management plan (Section 9.1.3.1),

Communications management plan (Section 10.1.3.1),

Risk management plan (Section 11.1.3.1),

Procurement management plan (Section 12.1.3.1), and

Stakeholder management plan (Section 13.2.3.1).

Among other things, the project management plan may also include the following:
Life cycle selected for the project and the processes that will be applied to each phase;

Details of the tailoring decisions specified by the project management team as follows:

○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
Description of how work will be executed to accomplish the project objectives;

Change management plan that documents how changes will be monitored and controlled;

Configuration management plan that documents how Configuration management will be performed;

Description of how the integrity of the project baselines will be maintained;

Requirements and techniques for communication among stakeholders; and

Key management reviews for content, the extent of, and timing to address, open issues and pending

decisions.
The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.
insert code

Question 540

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Correct Answer: A
Section: Volume C
Explanation/Reference:
insert code
  • ««
  • «
  • …
  • 104
  • 105
  • 106
  • 107
  • 108
  • 109
  • 110
  • 111
  • 112
  • 113
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.CAPM.v2022-04-08.q645 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.