FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. CAPM Exam
  4. PMI.CAPM.v2022-04-08.q645 Dumps
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
Download Now

Question 81

Which are the competing constraints that a project manager should address when tailoring a project?

Correct Answer: D
insert code

Question 82

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Correct Answer: A
Section: Volume C
Explanation:
4.1.1.1 Project Statement of Work
The project statement of work (SOW) is a narrative description of products, services, or results to be delivered by a project. For internal projects, the project initiator or sponsor provides the statement of work based on business needs, product, or service requirements. For external projects, the statement of work can be received from the customer as part of a bid document, (e.g., a request for proposal, request for information, or request for bid) or as part of a contract. The SOW references the following:
Business need. An organization's business need may be based on a market demand, technological advance,

legal requirement, government regulation, or environmental consideration. Typically, the business need and the cost-beneft analysis are contained in the business case to justify the project.
Product scope description. The product scope description documents the characteristics of the product,

service, or results that the project will be undertaken to create. The description should also document the relationship between the products, services, or results being created and the business need that the project will address.
Strategic plan. The strategic plan documents the organization's strategic vision, goals, and objectives and

may contain a high-level mission statement. All projects should be aligned with their organization's strategic plan. Strategic plan alignment ensures that each project contributes to the overall objectives of the organization.
insert code

Question 83

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

Correct Answer: D
Section: Volume A
Explanation:
Checksheets, which are also known as tally sheets and may be used as a checklist when gathering data.
Checksheets are used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem. They are especially useful for gathering attributes data while performing inspections to identify defects. For example, data about the frequencies or consequences of defects collected in checksheets are often displayed using Pareto diagrams.
insert code

Question 84

A project charter is an output of which Process Group?

Correct Answer: C
Explanation/Reference:
Explanation:
4.2.1.1 Project Charter
Described in Section 4.1.3.1. The size of the project charter varies depending on the complexity of the project and the information known at the time of its creation. At a minimum, the project charter should define the high-level boundaries of the project. The project team uses the project charter as the starting point for initial planning throughout the Initiating Process Group.
4.1.3.1 Project Charter
The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It documents the business needs, assumptions, constraints, the understanding of the customer's needs and high-level requirements, and the new product, service, or result that it is intended to satisfy, such as:
Project purpose or justification,

Measurable project objectives and related success criteria,

High-level requirements,

Assumptions and constraints,

High-level project description and boundaries,

High-level risks,

Summary milestone schedule,

Summary budget,

Stakeholder list,

Project approval requirements (i.e., what constitutes project success, who decides the project is

successful, and who signs off on the project),
Assigned project manager, responsibility, and authority level, and

Name and authority of the sponsor or other person(s) authorizing the project charter.
insert code

Question 85

During which process of Project Cost Management does a project manager produce the cost baseline?

Correct Answer: C
Section: Volume E
Explanation/Reference: https://mymanagementguide.com/guidelines/project-management/cost-management/determining- project-budget/#proc
insert code
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.CAPM.v2022-04-08.q645 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.