FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. CAPM Exam
  4. PMI.CAPM.v2022-04-08.q645 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 6

What is one of the objectives of Project Risk Management?

Correct Answer: C
Explanation/Reference:
Explanation:
PROJECT RISK MANAGEMENT
Project Risk Management includes the processes of conducting risk management planning, identification, analysis, response planning, and controlling risk on a project. The objectives of project risk management are to increase the likelihood and impact of positive events, and decrease the likelihood and impact of negative events in the project.
insert code

Question 7

How can a project manager represent a contingency reserve in the schedule?

Correct Answer: A
Section: Volume E
Explanation/Reference: https://www.pmi.org/learning/library/model-risk-contingency-reserve-9310
insert code

Question 8

The document that guides project execution, monitoring and control, and closure is called:

Correct Answer: B
Section: Volume E
Explanation/Reference: https://projectmanagementacademy.net/articles/five-traditional-process-groups/
insert code

Question 9

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

Correct Answer: D
Explanation/Reference:
Explanation:
12.1.3.1 Procurement Management Plan
The procurement management plan is a component of the project management plan that describes how a project team will acquire goods and services from outside the performing organization. It describes how the procurement processes will be managed from developing procurement documents through contract closure. The procurement management plan can include guidance for:
Types of contracts to be used;

Risk management issues;

Whether independent estimates will be used and whether they are needed as evaluation criteria;

Those actions the project management team can take unilaterally, if the performing organization has a

prescribed procurement, contracting, or purchasing department;
Standardized procurement documents, if needed;

Managing multiple suppliers;

Coordinating procurement with other project aspects, such as scheduling and performance reporting;

Any constraints and assumptions that could affect planned procurements;

Handling the long lead times to purchase certain items from sellers and coordinating the extra time

needed to procure these items with the development of the project schedule; Handling the make-or-buy decisions and linking them into the Estimate Activity Resources and Develop

Schedule processes
Setting the scheduled dates in each contract for the contract deliverables and coordinating with the

schedule development and control processes;
Identifying requirements for performance bonds or insurance contracts to mitigate some forms of project

risk;
Establishing the direction to be provided to the sellers on developing and maintaining a work breakdown

structure (WBS);
Establishing the form and format to be used for the procurement/contract statements of work;

Identifying prequalified sellers, if any, to be used; and

Procurement metrics to be used to manage contracts and evaluate sellers.

A procurement management plan can be formal or informal, can be highly detailed or broadly framed, and is based upon the needs of each project.
insert code

Question 10

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

Correct Answer: D
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.CAPM.v2022-04-08.q645 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.