FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. CAPM Exam
  4. PMI.CAPM.v2022-04-08.q645 Dumps
  • ««
  • «
  • …
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • 69
  • 70
  • 71
  • …
  • »
  • »»
Download Now

Question 326

Which are the competing constraints that a project manager should address when tailoring a project?

Correct Answer: A
Explanation/Reference:
Explanation:
Tailoring is necessary because each project is unique; not every process, tool, technique, input, or output identified in the PMBoK® Guide is required on every project. Tailoring should address the competing constraints of scope, schedule, cost, resources, quality, and risk. In addition, consideration of whether the customer of the project is internal or external to the organization may affect project management tailoring decisions. Sound project management methodologies take into account the unique nature of projects and allow tailoring, to some extent, by the project manager. However, the tailoring that is included in the methodology may still require additional tailoring for a given project. And that brings us to the end of Tailoring.n
insert code

Question 327

A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project manager's sphere of influence does this represent?

Correct Answer: C
Section: Volume E
Explanation/Reference:
insert code

Question 328

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Correct Answer: B
Section: Volume B
Explanation:
6.6.2.3 Critical Chain Method
The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method. To do so, the critical chain method introduces the concept of buffers and buffer management. The critical chain method uses activities with durations that do not include safety margins, logical relationships, and resource availability with statistically determined buffers composed of the aggregated safety margins of activities at specified points on the project schedule path to account for limited resources and project uncertainties. The resource-constrained critical path is known as the critical chain.
The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty.
One buffer, placed at the end of the critical chain, as shown in Figure 6-19, is known as the project buffer and protects the target finish date from slippage along the critical chain. Additional buffers, known as feeding buffers, are placed at each point where a chain of dependent activities that are not on the critical chain feeds into the critical chain. Feeding buffers thus protect the critical chain from slippage along the feeding chains.
The size of each buffer should account for the uncertainty in the duration of the chain of dependent activities leading up to that buffer. Once the buffer schedule activities are determined, the planned activities are scheduled to their latest possible planned start and finish dates. Consequently, instead of managing the total float of network paths, the critical chain method focuses on managing the remaining buffer durations against the remaining durations of chains of activities.

Figure 6-19. Example of Critical Chain Method
insert code

Question 329

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Correct Answer: D
insert code

Question 330

Which tool or technique is used in Close Procurements?

Correct Answer: D
Explanation/Reference:
Explanation:
12.4.2.1 Procurement Audits
A procurement audit is a structured review of the procurement process originating from the Plan Procurement Management process through Control Procurements. The objective of a procurement audit is to identify successes and failures that warrant recognition in the preparation or administration of other procurement contracts on the project, or on other projects within the performing organization.
12.4 Close Procurements
The process of completing each project procurement.
Key Benefit: The key benefit of this process is that it documents agreements and related documentation for future reference.
Inputs
1. Project management plan
2. Procurement documents
Tools & Techniques
1. Procurement audits
2. Procurement negotiations
3. Records management system
Outputs
1. Closed procurements
2. Organizational process assets updates
insert code
  • ««
  • «
  • …
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • 69
  • 70
  • 71
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.CAPM.v2022-04-08.q645 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.