Which Project Time Management process includes bottom-up estimating as a tool or technique?
Correct Answer: A
Explanation/Reference: Explanation: Process: 6.4 Estimate Activity Resources Definition: The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. Key Benefit: The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates. Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Resource calendars 5. Risk register 6. Activity cost estimates 7. Enterprise environmental factors 8. Organizational process assets Tools & Techniques 1. Expert judgment 2. Alternative analysis 3. Published estimating data 4. Bottom-up estimating 5. Project management software Outputs 1. Activity resource requirements 2. Resource breakdown structure 3. Project documents updates
Question 452
Project management processes ensure the:
Correct Answer: D
Section: Volume B Explanation Explanation: Project management processes. These processes ensure the effective flow of the project throughout its life cycle. These processes encompass the tools and techniques involved in applying the skills and capabilities described in the Knowledge Areas (Sections 4 through 13)
Question 453
Which tool or technique is used in Manage Stakeholder Expectations?
Correct Answer: D
Question 454
Which of the following processes are part of the Project Integration Management Knowledge Area?