FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. CAPM Exam
  4. PMI.CAPM.v2022-10-10.q958 Dumps
  • ««
  • «
  • …
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • …
  • »
  • »»
Download Now

Question 51

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members.
This situation describes which type of organizational structure?

Correct Answer: D
insert code

Question 52

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable.
This could have been avoided if the project team had implemented:

Correct Answer: C
insert code

Question 53

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Correct Answer: C
Explanation/Reference:
A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity.
For example, a technical writing team may begin editing the draft of a large document 15 days after they begin writing it.
Process: 6.3 Sequence Activities
Definition: The process of identifying and documenting relationships among the project activities.
Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Milestone list
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets
Tools & Techniques
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Leads and lags
Outputs
1. Project schedule network diagrams
2. Project documents updates
insert code

Question 54

The following is a network diagram for a project.

What is the critical path for the project?

Correct Answer: C
Section: Volume B
insert code

Question 55

Which of the following is a strategy to deal with positive risks or opportunities?

Correct Answer: C
Section: Volume E
Explanation:
11.5.2.2 Strategies for Positive Risks or Opportunities
Three of the four responses are suggested to deal with risks with potentially positive impacts on project objectives.
The fourth strategy, accept, can be used for negative risks or threats as well as positive risks or opportunities.
These strategies, described below, are to exploit, share, enhance, and accept.
Exploit. The exploit strategy may be selected for risks with positive impacts where the organization wishes to

ensure that the opportunity is realized. This strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring the opportunity definitely happens. Examples of directly exploiting responses include assigning an organization's most talented resources to the project to reduce the time to completion or using new technologies or technology upgrades to reduce cost and duration required to realize project objectives.
Enhance. The enhance strategy is used to increase the probability and/or the positive impacts of an

opportunity. Identifying and maximizing key drivers of these positive-impact risks may increase the probability of their occurrence. Examples of enhancing opportunities include adding more resources to an activity to finish early.
Share. Sharing a positive risk involves allocating some or all of the ownership of the opportunity to a third

party who is best able to capture the opportunity for the beneft of the project. Examples of sharing actions include forming risk-sharing partnerships, teams, special-purpose companies, or joint ventures, which can be established with the express purpose of taking advantage of the opportunity so that all parties gain from their actions.
Accept. Accepting an opportunity is being willing to take advantage of the opportunity if it arises, but not

actively pursuing it.
insert code
  • ««
  • «
  • …
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.CAPM.v2022-10-10.q958 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.