FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. CAPM Exam
  4. PMI.CAPM.v2022-10-10.q958 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 11

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Correct Answer: D
Section: Volume E
insert code

Question 12

An output of the Create WBS process is:

Correct Answer: A
Explanation/Reference:
Explanation:
5.4.3.1 Scope Baseline
The scope baseline is the approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include:
Project scope statement. The project scope statement includes the description of the project scope,

major deliverables, assumptions, and constraints.
WBS. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project

team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information. A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to the earned value for performance measurement. Control accounts are placed at selected management points in the WBS. Each control account may include one or more work packages, but each of the work packages should be associated with only one control account. A control account may include one or more planning packages. A planning package is a work breakdown structure component below the control account with known work content but without detailed schedule activities.
WBS dictionary. The WBS dictionary is a document that provides detailed deliverable, activity, and

scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Information in the WBS dictionary may include, but is not limited to:
○ Code of account identifier,
○ Description of work,
○ Assumptions and constraints,
○ Responsible organization,
○ Schedule milestones,
○ Associated schedule activities,
○ Resources required,
○ Cost estimates,
○ Quality requirements,
○ Acceptance criteria,
○ Technical references, and
○ Agreement information
Process: 5.4 Create WBS
Definition: WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. Key Benefit: The key benefit of this process is that it provides a structured vision of what has to be delivered.
Inputs
1. Scope management plan
2. Project scope statement
3. Requirements documentation
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Decomposition
2. Expert judgment
Outputs
1. Scope baseline
2. Project documents updates
insert code

Question 13

When managing costs in an agile environment, what should a project manager consider?

Correct Answer: B
insert code

Question 14

Why is tailoring required in a project?

Correct Answer: B
Section: Volume E
Explanation/Reference:
insert code

Question 15

In an organization with a projectized organizational structure, who controls the project budget?

Correct Answer: B
Section: Volume C
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.CAPM.v2022-10-10.q958 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.