FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMI-PBA Exam
  4. PMI.PMI-PBA.v2026-01-17.q214 Dumps
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
Download Now

Question 42

Which statement accurately depicts what changes can be made to requirements after they are baselined?

Correct Answer: A
The main output is the scope baseline, which consists of three documents; the scope statement (including both project and product requirements), the WBS(s), and the WBS dictionary. These are reviewed and upon approval, the scope baseline is created. Once that baseline has been approved, changes can only be made through a change control procedure. The scope baseline will be used to continually compare the actual results and work being done on the project to the original, approved scope.
insert code

Question 43

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.
Which is a possible reason why the requirement was not implemented?

Correct Answer: C
A requirements traceability matrix is a tool that links the requirements to their sources, objectives, and deliverables. It helps to track the status, changes, and verification of each requirement throughout the project life cycle. If the requirements traceability matrix was not updated with the change, it could result in a key requirement being missed or overlooked in the implementation. The other options are not likely to cause this problem. The requirements management plan is a document that describes how the requirements will be elicited, analyzed, documented, validated, and managed. The scope management plan is a document that describes how the project scope will be defined, controlled, and verified. The schedule management plan is a document that describes how the project schedule will be developed, monitored, and controlled. References:
PMI-PBAExamination Content Outline, page 13; PMI-PBAReference List, page 1, BABOK Guide v3, page 39; 6.
insert code

Question 44

Which of the following best describes the function of the requirements baseline?

Correct Answer: A
insert code

Question 45

A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?

Correct Answer: D
insert code

Question 46

A business analyst captures an application's current limitations and consults with end users to identify new features for the next version. What can be used to analyze this information and determine project scope?

Correct Answer: C
Explanation/Reference: https://www.lucidchart.com/blog/as-is-process-analysis
insert code
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMI-PBA.v2026-01-17.q214 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.