You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?
The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.
If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?
You work as a project manager for BlueWell Inc. You are working with Nancy, the COO of your company, on several risks within the project. Nancy understands that through qualitative analysis you have identified 80 risks that have a low probability and low impact as the project is currently planned. Nancy's concern, however, is that the impact and probability of these risk events may change as conditions within the project may change. She would like to know where will you document and record these 80 risks that have low probability and low impact for future reference. What should you tell Nancy?
You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification?