FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMI-RMP Exam
  4. PMI.PMI-RMP.v2024-03-25.q113 Dumps
  • ««
  • «
  • …
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • …
  • »
  • »»
Download Now

Question 46

Jeff, a key stakeholder in your project, wants to know how the risk exposure for the risk events is calculated during quantitative risk analysis. He is worried about the risk exposure which is too low for the events surrounding his project requirements. How is the risk exposure calculated?

Correct Answer: D
insert code

Question 47

The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?

Correct Answer: A
insert code

Question 48

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?

Correct Answer: A
Explanation
According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain of Risk Identification is to use the information from project documents, lessons learned, and other sources to facilitate the risk identification process1. A risk workshop is a tool and technique for risk identification that involves bringing together the project team, stakeholders, subject matter experts, and risk management experts to identify and analyze the project risks in a structured and collaborative manner2. In this scenario, the risk manager should use the information from the issues and unexpected results found in the first phase of the project for a risk workshop, to avoid the previous issues in the next phase. The risk workshop will help the risk manager and the project team to identify the root causes of the issues, assess their probability and impact, and develop appropriate risk responses. The risk workshop will also enable the risk manager to update the risk register and the risk report with the new information and communicate the risk status to the relevant stakeholders. The risk manager should not improve monitoring and controlling of activities, because that is not a specific action to avoid the previous issues, but rather a general practice that should be done throughout the project life cycle3. The risk manager should not document the issues in the lessons learned, because that is not enough to avoid the previous issues, but rather a way to capture and share the knowledge gained from the project for future reference4. The risk manager should not create an issue log to share with the team, because that is not a proactive risk management technique, but rather a reactive way to track and resolve the issues that have already occurred5. References: 1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 82: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, page 4003: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, page 4564: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, page 1005: What Is an Issue Log? Templates & Tips6.
insert code

Question 49

You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?

Correct Answer: D
insert code

Question 50

The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?

Correct Answer: C
insert code
  • ««
  • «
  • …
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMI-RMP.v2024-03-25.q113 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.