An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
Correct Answer: B
Explanation The risk management plan is a document that describes how risk management activities will be structured and performed on a project. It defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms1. The risk management plan should be aligned with the project management plan, which defines the project scope, schedule, cost, quality, and other aspects2. When an organization decides to accelerate a key project, it means that the project objectives, assumptions, constraints, and environment have changed. This will affect the risk exposure and profile of the project, as well as the risk management approach and resources. Therefore, the first action for the project risk manager to take is to revise the risk management plan to reflect the new situation and ensure that the risk management process is still effective and efficient. Revising the risk management plan may involve updating the risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms to suit the accelerated project. The project risk manager should also communicate the revised risk management plan to the relevant stakeholders and obtain their approval and support1. Ensuring sufficient resources are available, updating the risk register, and meeting with the project's stakeholders are all important actions to take when accelerating a project, but they are not the first action. These actions should be done after revising the risk management plan, as they depend on the updated risk management approach and process. For example, the project risk manager may need to allocate more resources to risk management activities, identify and analyze new or changed risks, implement new or modified risk responses, and report the risk status and performance to the stakeholders based on the revised risk management plan1. References: 2, 1. When a project is accelerated, the risk landscape changes. The project risk manager should first revise the risk management plan to address the new timeline and its potential impacts on the project. This will help in identifying new risks, reassessing existing risks, and updating risk responses.
Question 62
Jeff, a key stakeholder in your project, wants to know how the risk exposure for the risk events is calculated during quantitative risk analysis. He is worried about the risk exposure which is too low for the events surrounding his project requirements. How is the risk exposure calculated?
Correct Answer: B
Question 63
Which one of the following is the only output for the qualitative risk analysis process?
Correct Answer: C
Question 64
Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost- plus contract. If Don were to perform a risk audit, who would carry the risk in this scenario?
Correct Answer: B
Question 65
Adrian is a project manager for a new project using a technology that has recently been released and there's relatively little information about the technology. Initial testing of the technology makes the use of it look promising, but there's still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses?