FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PfMP Exam
  4. PMI.PfMP.v2023-01-21.q102 Dumps
  • ««
  • «
  • …
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • …
  • »
  • »»
Download Now

Question 31

As you work to determine which stakeholders had the highest degree of influence over the portfolio, you wanted to especially know about the members of the Portfolio Governance Board because:

Correct Answer: D
insert code

Question 32

In a portfolio, data is an abundant asset, and managing the information aiming for a better decision making is critical. Which of the following are considered outputs to the Manage Portfolio Information process?

Correct Answer: B
insert code

Question 33

You have scored the portfolio components and are analyzing the data in order to prioritize the components.
Using the following scoring table, which of the options represents the correct Components Priority? Taking into consideration that the costs for each component is Component A: 10 K USD, Component B: 15 K USD, Component C: 16 K USD, Component D: 13 K USD and Component E: 11 K USD; The budget for this portfolio is a fixed one of 40 k USD Larger image

Correct Answer: D
Explanation
D, B, E is the correct prioritization sequence. First, you need to calculate the (Value*Weight) for each criteria for each component:
then, sum the three resulting columns into a total column:
The priority is from the highest to the lowest; Then, you need to accept the prioritized components until you reach the budget cap: Component D (13 K) + Component B (15 K) + Component E (11 K); Component E is the last accepted one before reaching the budget cap.
insert code

Question 34

Which of the following depicts the use of the burn-down and burn-up charts?

Correct Answer: D
insert code

Question 35

You are in the process of planning the portfolio for a major client and wanted to put an extra effort on planning for managing the performance as the portfolio has a lot of technical aspects and correct performance management is key to success. What tools and techniques can you use for this purpose?

Correct Answer: C
insert code
  • ««
  • «
  • …
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PfMP.v2023-01-21.q102 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.