What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?