Which is a typical core activity within configuration management?
Correct Answer: A
Question 39
Which product identifies how often stakeholders require information?
Correct Answer: A
The Communication Management Approach in PRINCE2 outlines the means and frequency of communication to stakeholders throughout the project. This document specifies how often stakeholders require updates and information regarding the project's progress and any issues that arise, ensuring that all parties are adequately informed. References: PRINCE2 7 Foundation Handbook and official training materials.
Question 40
What is an advantage of applying the 'manage by stages' principle?