The following settings are defined for a freight order from location A to location B with two freight units:
* The distance between locations A and B in the transportation lane is 1500 km, the duration is 19 hours and the Fix Transportation Duration flag is set. The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is NOT set.
Loading and unloading of each freight unit at locations A and B is defined as 1 hour.
The vehicle resource is available weekdays from 8:00 am to 8:00 pm.
* Loading starts on Monday at 8:30 am. When is unloading finished?
Please choose the correct answer.
The Core Interface or CIF is the technology that is used to transfer the master data from ERP to TM. Master data inormally scheduled for batch transfer once a day. The transfer of master data changes can be scheduled periodically as a job. You have to define a variant (containing the target system -TM - and the selection of master data objects) for the program RCPTRAN4 (hidden behind transaction CFP1).
Before you transfer the master-data, the following prerequisites need to be satisfied:
(2 correct answers)
What do you need to maintain to ensure that certain products are always shipped by air?
In the logistics integration profile, the Incoterm location stage building is set to "Source location to Incoterm location- type 1". You create a sales order in which you have specified an Incoterm and Incoterm location. What will be the result of these settings?
Organizational structures can be maintained directly in SAP TM. Determine whether this statement is true or false.