Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
You have saved a network and activates with assigned material components. As soon as you release the network,
you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?