You are using the Resource Location master data type. How do you specify capacity supply as time- dependent?
You want to display and edit data in different units of measure (UOM). Which of the following must you consider before you use UOM? Note: There are 3 correct Answers to this question.
Which of the following stages can be modeled using scenarios from the S&OP planning cycle? Note:
There are 2 correct Answers to this question.
Which SAP IBP planning operator can be run to delete planning objects in a certain version?