Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? Note: There are 2 correct answers to this question.
Which times are used for Basic Date Scheduling of manufacturing planned orders in MRP?
There are 2 correct answers to this question.
Response:
What is the equivalent in SAP S/4HANA of the Production Data Structure in PP/DS?
There are 3 correct answers to this question.
Response:
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
A planner updated a production order status from partially confirmed "PCNF" to technically completed "TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response: