FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. SAP Certification
  3. C_TS422_2023 Exam
  4. SAP.C_TS422_2023.v2025-03-19.q61 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 16

which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing?
Note: There are 3 Correct answers to this question.

Correct Answer: A,B,C
When you save a confirmation for a finished product in repetitive manufacturing, the system performs the following actions by default12:
Posting of production costs to the production cost collector: The system calculates the actual costs for the confirmed quantity and posts them to the production cost collector assigned to the product. The production cost collector is a cost object that collects the costs for all confirmations of a product in a plant for a period.
Posting of goods receipt for the product: The system posts the confirmed quantity as a goods receipt to the warehouse. The product is valuated at the standard price defined in the material master record. The difference between the standard price and the actual costs is posted to a price difference account.
Reduction of associated capacity requirements: The system reduces the capacity requirements for the work center where the confirmation was made. The capacity requirements are calculated based on the confirmed quantity and the standard values for setup, machine, and labor time in the routing. Reference: 1: Repetitive Manufacturing Confirmation | SAP Help Portal(https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/ee6ff9b281d8448f96b4fe6c89f2bdc8/66dd7fc2d4ac4a53b51f300a04ae24ac.html)2: Confirming Production in Repetitive Manufacturing | SAP Help Portal(https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/9231f9504a62eb5ee10000000a44538d.html).
insert code

Question 17

Which time elements can be reduced by a reduction strategy?
Note: There are 3 correct answers to this question.

Correct Answer: B,C,E
A reduction strategy is a method of shortening the lead time of an order by reducing certain time elements in the order scheduling1. The time elements that can be reduced by a reduction strategy are move time, wait time, and queue time2. Move time is the time required to move a material from one operation to another. Wait time is the time between the end of an operation and the start of the next operation. Queue time is the time before an operation can start at a work center due to the work center's capacity utilization3. These time elements can be reduced by a percentage or a fixed value in the reduction strategy. Reference: 1: Reduction Strategy | SAP Help Portal(https://blog.sap-press.com/4-strategies-for-make-to-stock-production-with-sap-s4hana)2: 4 Strategies for Make-to-Stock Production with SAP S/4HANA(https://blogs.sap.com/2022/03/22/highlights-for-manufacturing-in-sap-s-4hana-2021-part-2-production-planning-engineering-operations/)3: Scheduling | SAP Help Portal(https://blogs.sap.com/2022/04/26/manufacturing-in-sap-s-4hana-cloud-planning-strategies/).
insert code

Question 18

You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

Correct Answer: B
Consumption-based planning is a planning procedure that uses past consumption data to calculate the future requirements of materials. It does not consider the dependent requirements of higher-level materials, but only the independent requirements from sales orders, forecasts, or stock transfers. Consumption-based planning is suitable for B and C materials, which have low value, low demand variability, and high availability. Consumption-based planning reduces the planning efforts for these materials, as it does not require the maintenance of BOMs, routings, or production versions. Consumption-based planning can be further divided into reorder point planning, forecast-based planning, and time-phased planning, depending on the method of determining the reorder point and the lot size12 Reference:
Consumption-Based Planning - SAP Help Portal
SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 3: Material Requirements Planning, Section 3.1: Planning Procedures, Page 67
insert code

Question 19

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.
Note: there are 2 correct answers to this question.

Correct Answer: A,B
Alternative item strategies are used to define how the system selects the alternative items in a BOM during the planning run or the order creation. The following alternative item strategies are available in SAP S/4HANA:
Manual maintenance: The system does not select any alternative item automatically. You have to manually select the alternative item in the BOM or the order. This strategy is useful when you want to have full control over the alternative item selection and when the selection depends on factors that are not known to the system1
100% check: The system checks the availability of all alternative items and selects the one with the highest priority and sufficient stock. If none of the alternative items has enough stock, the system selects the one with the highest priority and the smallest shortage quantity. This strategy is useful when you want to optimize the material availability and reduce the procurement costs2 First in First out (FIFO): The system selects the alternative item with the highest priority and the earliest availability date. If several alternative items have the same availability date, the system selects the one with the highest priority. This strategy is useful when you want to use the oldest stock first and avoid obsolescence3 Simultaneous: The system selects all alternative items simultaneously and distributes the requirement quantity among them according to the usage probability. The usage probability is a percentage value that indicates how often an alternative item is used. This strategy is useful when you want to balance the demand and supply of multiple alternative items and when the usage probability is known.
Reference:
Alternative Item Group - SAP Help Portal
Alternative Item Group - SAP Help Portal
Alternative Item Group - SAP Help Portal
[Alternative Item Group - SAP Help Portal]
insert code

Question 20

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

Correct Answer: B,D
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download SAP.C_TS422_2023.v2025-03-19.q61 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.